In development · South West Queensland
Punch's Creek Stage 2
A 400 MW solar and 1,600 MWh storage stage in the South West Queensland REZ, moving through grid connection with Powerlink.
Project detail
- Solar capacity
- 400 MW / 420 MWp
- BESS
- 400 MW / 1,600 MWh BESS
- Grid connection
- Powerlink 330 kV, new 400 MW connection
- Land tenure
- 30 year + lease option
- Status
- Grid performance standards stage
- Location
- South West Queensland Renewable Energy Zone
Punch’s Creek Renewable Energy is a proposed renewable energy project consisting of two stages, located in the heart of the South West Queensland Renewable Energy Zone. Stage 2 is 400 MW / 420 MWp of solar with a 400 MW / 1,600 MWh BESS.
With direct access to the Powerlink Transmission Network, this site provides the ultimate balance between connection and opportunity.
The site is located on prime land with a 30 year + lease option and has already obtained significant support from the local community.
The project received full development approval in Q1 2024, and EPBC approval in Q2 2024.
The Stage 2 part of the project will connect to the Powerlink 330 kV transmission line via a new 400 MW connection into the existing substation and line that traverses the site. The project is on track to execute an early works agreement with Powerlink in 2026, with a Q4 2028 connection.
SkyLab Australia is currently moving through the GPS stage after submitting the connection application in Q4 2025.
Punch’s Creek Renewable Energy is proposing to commence construction in Q2 2027 of the substation connection and have commercial operation by Q1 2029 for Stage 2.
Development pathway
Milestones.
- Q1 2024Full development approval received
- Q2 2024EPBC approval received
- Q4 2025Grid connection application submitted
- 2026Early works agreement with Powerlink
- Q2 2027Construction of substation connection begins
- Q4 2028Grid connection
- Q1 2029Commercial operation
On site


Site layout and approvals
The plans behind it.


SkyLab welcomes parties interested in Stage 2. There are considerable leverage advantages carried over from Stage 1.
Discuss Stage 2Keep exploring
Other projects.
The next chapter starts here
Let’s build
what comes next.
Great projects begin with the right conversation.