Proposed development · South Australia
South East Adelaide
Co-development - gas, BESS & data centre
A proposed co-development combining 1.2 GW of data centre load, 400 MW / 1,600 MWh grid-forming BESS and 600 MW of gas generation, with first power targeted for Q1 2029.
Project detail
- Proposed DC load
- 1.2 GW
- Grid-forming BESS
- 400 MW / 1,600 MWh
- Gas generation
- 600 MW
- First power
- Q1 2029
- Location
- Approx. 120 km south-east of Adelaide, South Australia
Images show indicative infrastructure, not site photographs or approved project designs.
SkyLab Australia is developing a large project development in South Australia, approximately 120 km south-east of Adelaide.
The site has strong transmission network access, high volume potential water supply, ultra low latency fibre duplicate communications network, mains gas, and borders the main highway between Adelaide, South Australia and Melbourne, Victoria.
Our team has commenced working closely with key stakeholders in the South Australian Government, utilities and data centre operators to secure the long term need for the site.
Why this site
- Strong transmission network access
- High volume potential water supply
- Ultra low latency duplicate fibre
- Mains gas
- Borders the Adelaide–Melbourne highway
Indicative project components



We welcome conversations about this project.
Talk to our teamKeep exploring